Videberg Kraft continues towards new nuclear
Videberg Kraft continues to take important steps in the development of new nuclear power on the Värö Peninsula next to Ringhals. During the year, several fundamental conditions for the project have been put in place. At the same time, work on areas including permitting, supplier collaboration, and site and logistics is entering a more intensive phase.
Videberg Kraft continues to take important steps in the development of new nuclear power on the Värö Peninsula next to Ringhals. During the year, several fundamental conditions for the project have been put in place. At the same time, work on areas including permitting, supplier collaboration, and site and logistics is entering a more intensive phase.
The company is developing its capabilities to plan, build and, in the longer term, operate new nuclear reactors safely, cost-effectively and competitively. During the summer, a new Board of Directors was appointed and a new management structure was established, with Patrick Guné due to take up the role of CEO on 1 November.
Several important conditions have also become clearer. The County Administrative Board's decision to revoke part of the Biskopshagen nature reserve, 25 of its 83 hectares, has created the conditions for continued work on the application to the Land and Environment Court.
In parallel, preparations are continuing for the application documents to be submitted to the Swedish Radiation Safety Authority, following the selection of Rolls-Royce SMR as the final technology supplier in June. The Swedish Government has also submitted an application to the European Commission for state aid approval.
State aid approval is crucial to the financing
The European Commission will assess whether the agreed state aid model is compatible with EU state aid rules. The model includes government loans, price hedging through two-way contracts for difference, and a risk- and profit-sharing model. The Government expects that the Commission may reach a decision in autumn 2027.
The assessment is an important prerequisite for the project's continued development. Only after approval can the state financing take full effect and the Swedish state's planned acquisition of 60 per cent of the shares in Videberg Kraft be completed. Until then, the company will continue working on the other parts of the project.
The state aid assessment is one of several processes that must be completed before a final investment decision can be made within the next few years.
Permitting work enters an intensive phase
Work on the project's applications has now entered a phase in which the supporting documentation is gradually being finalised and anchored across the entire project organisation. This includes the application to the Land and Environment Court, the environmental impact assessment, the application under the Nuclear Activities Act and work on the detailed development plan. The environmental impact assessment is a central component of several of these processes.
An important premise is that the application documents must reflect Videberg Kraft's own positions.
“The applications must demonstrate that we understand the facility, what it means to build and operate it, and the responsibilities that come with being a licence holder. The next step is to finalise the documentation, continue the close dialogue with the relevant authorities and submit the applications around the turn of the year,” says Fredrik Hassel, Head of Permitting and Licensing at Videberg Kraft.
The permitting work is closely linked to several technical and environmental choices. These include the design of the facility, the possibility of using the existing port at Ringhals, and how impacts on the natural environment are to be managed and compensated for. Dialogue with authorities, the municipality, local residents and other affected stakeholders will therefore remain important throughout the process, and new information will be provided and updated regularly.
Next steps in supplier collaboration
The selection of Rolls-Royce SMR was an important milestone. Work is now continuing to translate the technology choice into a long-term and effective delivery partnership.
The focus is on establishing the basis for the first major supply agreement. Among other things, the agreement will describe what is to be delivered, when the work is to be carried out, which requirements must be met, and how costs and responsibilities are to be managed. At the same time, the work is laying the foundation for the project's continued development ahead of a future investment decision.
“This is about considerably more than agreeing commercial terms. Together with Rolls-Royce SMR, we need to define how the work will be conducted, which requirements arise from the Swedish context, and how the deliveries will be planned and packaged. The work we are doing now is laying the foundation for the collaboration over the coming years,” says Arvid Gällström, Head of Supply Chain and Contracting at Videberg Kraft.
The work requires close interaction between the different parts of the project. Expertise in areas including technology, permitting, site, procurement and commercial matters needs to be brought together around a shared set of requirements. Videberg Kraft and Rolls-Royce SMR have begun this joint work and are now continuing to develop ways of working, plans and the allocation of responsibilities.
The site and logistics are being planned
Work on the site includes securing the land required by the project, planning how the area is to be designed and determining how construction can be carried out. It also includes compensatory measures for the natural environment, as well as matters relating to the port, roads, transport, grid connection and other infrastructure.
At the same time, the project needs to plan how materials, components and people can be transported to and from the area during the construction period. Several of these matters have long lead times and require early discussions with Rolls-Royce SMR, Ringhals, the municipalities concerned, landowners and infrastructure operators, among others.
“We have taken important steps to secure the conditions at the site. We now need to develop an integrated plan covering areas such as transport, the port solution, accommodation and the infrastructure required for construction. Many of these matters have long lead times, so the work must begin well before all the details of the construction plan have been finalised,” says Kenneth Bundy, Head of Site and Logistics at Videberg Kraft.
A project with many interdependencies
The development of new nuclear power is a complex undertaking in which technology, permitting, financing, supplier collaboration and local community planning need to progress in parallel. Progress in one area often creates the conditions for the next, while new issues need to be analysed and resolved along the way.
Videberg Kraft continues to develop the project together with the technology supplier, authorities, the municipality, local residents and other affected stakeholders, in order to build, step by step, a robust basis for all forthcoming decisions and for the safe and responsible establishment of new nuclear power in Sweden.
About the project
Videberg Kraft AB is owned by Vattenfall AB and Industrikraft i Sverige AB, and in the long term also the Swedish state. Together, the owners combine Swedish industrial expertise, nuclear know-how and long-term ownership to strengthen Sweden's competitiveness and secure the electricity supply for future generations.