Our path to new nuclear power

Developing and building nuclear power is an extensive process. Here, we outline the key steps, from early studies to a complete plant producing fossil-free electricity for decades to come.

ExploreWe assessed the site, technology and suppliers, project economics and financing.
Completed

In 2022, Vattenfall initiated a pre-study to explore the potential for new nuclear power. The study concluded that the Värö Peninsula is a well-suited location for the development. In parallel, potential suppliers were evaluated.

In April 2026, Videberg Kraft took over responsibility for the project, and in June 2026, Rolls-Royce SMR was selected as the supplier.

The Värö peninsula, where the new reactors are planned.
SitePotential sites were assessed, and the Värö Peninsula selected as the preferred location.
Technology and supplierReactor technologies and potential suppliers were assessed, resulting in the selection of Rolls-Royce SMR.
Project economics and financingThe commercial viability of the project was analysed.
OrganisationThe conditions for carrying out the project were evaluated and Videberg Kraft was formed.
2
DevelopWe prepare the facility, apply for permits, secure financing and advance the project towards the start of construction.
We are here
Right now
Focus on consultation & applicationsWe are preparing the documentation for applications under the Nuclear Activities Act and the Environmental Code and conducting consultations on how the project should be designed.
Next step
Once the documentation is complete, the applications are submitted for review by the Swedish Radiation Safety Authority (SSM), the Land and Environment Court and the municipality. The Government will then decide on the permit and permissibility.
Consultation, permitting and regulatory review
Three reviews, partly at the same timeThe project is reviewed under three laws, by different authorities. When all permits are in place, we can make an investment decision.
Videberg Kraft
Authority, court, the Government or the municipality
Nuclear Activities Act
SSM
Videberg Kraft:Application
SSM's opinion
Government permit
Permission to build
Environmental Code
Land and Environment Court
Videberg Kraft:ConsultationTo the consultation
Videberg Kraft:Application
The court's opinion
Government permissibility
Environmental permit
Planning and Building Act
The municipality
Detailed development plan
Building permit
Investment decision
Construction startsStep 3
Ongoing throughout:organisation, project planning, economics and financing
Continues in steps 3 and 4
SSM provides its opinion on nuclear safety and radiation protection. The Land and Environment Court provides its opinion on the environmental permit, while the municipality has a right of veto. The Government decides on the permit under the Nuclear Activities Act and on permissibility under the Environmental Code.
When the permits are in place and the Government has granted permissibility, an investment decision can be made, that is, a decision to start building new reactors on the Värö peninsula.
3
BuildWe prepare the site and build the reactors on the Värö Peninsula.

Before construction of the new reactors begins, the site and other infrastructure will be prepared. Construction will continue for several years.

4
CommissionWe test and commission the plant before it enters commercial operation.

When the plant is complete, a period of testing and trial operation follows. The purpose is to make sure that the plant, the technology and the organisation work as they should before the reactors go into commercial operation.

The ambition is for the first modular nuclear reactor to be in operation in the mid-2030s at the earliest.

Visualisation of the planned plant on the Värö peninsula, seen from the small-boat harbour
Note – the image is for illustration only.
Note – the image is for illustration only.

The Site

The Värö peninsula in Varberg Municipality, where the Ringhals nuclear power plant is already located, was identified early on as the most suitable site for new nuclear power in Sweden. One important factor is that the area is designated as an area of national interest for energy production.

Its location in the southern part of the country is another clear advantage. Electricity generation in the south currently falls short of demand, and electricity prices have therefore been higher than in northern Sweden. New nuclear power in south-western Sweden could benefit both consumers and energy-intensive industries through lower and more predictable electricity prices.

The region also has extensive nuclear expertise and experience built up through the existing Ringhals reactors. There are also opportunities to make use of shared infrastructure, such as the grid connection.

The support from the local community is important, not only to the success of the project but also for the operation of the plant throughout its long lifetime.

Do you live near the Värö peninsula? Read more here
Two people in Rolls-Royce SMR vests walk past a pipework module in a factory hall

The Supplier

Rolls-Royce SMR combines proven nuclear technology with a standardised, modular approach to construction.

The vast majority of the plant is manufactured and tested in factories before being delivered as modules. The power plants are then assembled on site in a protected environment, reducing the impact of weather on construction, providing a better working environment and reducing the impact on local residents.

Rolls-Royce SMR is also the selected supplier for ČEZ and GBE-N. Being part of a European fleet with a supply chain in the region is a significant advantage.

The reactor vessel in one of the Ringhals reactors

The Technology

Like all nuclear power technologies, modular reactors generate electricity through the controlled fission of uranium atoms in a reactor core.

In the reactor, water is heated by the energy released through nuclear fission. The heat is then transferred to a separate system where water turns into steam. The steam drives a turbine, which in turn drives the generators that produce electricity.

Most nuclear power plants, including those currently operating in Sweden, use so-called light water reactor technology, primarily in the form of boiling water reactors (BWRs) or pressurised water reactors (PWRs).

Videberg Kraft has selected the reactor type and number of reactors: three modularly built pressurised water reactors with a combined thermal output of up to about 4,200 MW, expected to produce about 12 TWh of electricity per year.

Compared to traditional reactors, modular reactors have a larger share of prefabricated components that are assembled on site. This enables considerably shorter construction times and makes the technology scalable, while requiring less on-site labour than traditional reactors – which in turn drives cost savings.

Read more about the technology on the Rolls-Royce SMR website