Our path to new nuclear power
Developing and building nuclear power is an extensive process. Here, we outline the key steps, from early studies to a complete plant producing fossil-free electricity for decades to come.
ExploreWe assessed the site, technology and suppliers, project economics and financing.Completed
In 2022, Vattenfall initiated a pre-study to explore the potential for new nuclear power. The study concluded that the Värö Peninsula is a well-suited location for the development. In parallel, potential suppliers were evaluated.
In April 2026, Videberg Kraft took over responsibility for the project, and in June 2026, Rolls-Royce SMR was selected as the supplier.

DevelopWe prepare the facility, apply for permits, secure financing and advance the project towards the start of construction.We are here
Following the selection of Rolls-Royce SMR as technology supplier, the work is now moving into the next phase: developing the plant design and adapting it to the specific conditions at the Värö Peninsula.
The technical work is closely linked to the permitting process. The design needs to provide the basis for the applications being prepared now and will continue to be developed in greater detail as the project progresses towards an investment decision and, subject to the necessary permits, construction.
What we are focusing on now:
- Developing and adapting the Rolls-Royce SMR design to the conditions at the Värö Peninsula
- Defining technical requirements together with Rolls-Royce SMR
- Planning the site, port, transport, grid connection and other infrastructure
- Developing the basis for the first major supply agreement with Rolls-Royce SMR
- Preparing for the more detailed design and execution planning that follows later in the project
An important part is the financing of the project. The Swedish Government has submitted the proposed state aid model to the European Commission for approval under EU state aid rules. The model includes government loans, price hedging through two-way contracts for difference, and a mechanism for sharing risk and returns.
State aid approval is a prerequisite for the project’s continued development. Once approved, the state financing can take full effect and the Swedish state’s planned acquisition of 60 per cent of the shares in Videberg Kraft can be completed.
The financing process, permitting, technical development, plan for waste management, and project planning all need to come together before a final investment decision can be made.
What we are focusing on now:
- Developing the organisation and capabilities needed to deliver the project
- Developing the overall project and execution plans
- Preparing the project for a future investment decision
- Developing commercial arrangements and the basis for major supplier agreements
- Progressing the financing framework while the European Commission reviews the proposed state aid model
- Assessing waste management plan
BuildWe prepare the site and build the reactors on the Värö Peninsula.
Before construction of the new reactors begins, the site and other infrastructure will be prepared. Construction will continue for several years.
CommissionWe test and commission the plant before it enters commercial operation.
When the plant is complete, a period of testing and trial operation follows. The purpose is to make sure that the plant, the technology and the organisation work as they should before the reactors go into commercial operation.
The ambition is for the first modular nuclear reactor to be in operation in the mid-2030s at the earliest.

The Site
The Värö peninsula in Varberg Municipality, where the Ringhals nuclear power plant is already located, was identified early on as the most suitable site for new nuclear power in Sweden. One important factor is that the area is designated as an area of national interest for energy production.
Its location in the southern part of the country is another clear advantage. Electricity generation in the south currently falls short of demand, and electricity prices have therefore been higher than in northern Sweden. New nuclear power in south-western Sweden could benefit both consumers and energy-intensive industries through lower and more predictable electricity prices.
The region also has extensive nuclear expertise and experience built up through the existing Ringhals reactors. There are also opportunities to make use of shared infrastructure, such as the grid connection.
The support from the local community is important, not only to the success of the project but also for the operation of the plant throughout its long lifetime.

The Supplier
Rolls-Royce SMR combines proven nuclear technology with a standardised, modular approach to construction.
The vast majority of the plant is manufactured and tested in factories before being delivered as modules. The power plants are then assembled on site in a protected environment, reducing the impact of weather on construction, providing a better working environment and reducing the impact on local residents.
Rolls-Royce SMR is also the selected supplier for ČEZ and GBE-N. Being part of a European fleet with a supply chain in the region is a significant advantage.

The Technology
Like all nuclear power technologies, modular reactors generate electricity through the controlled fission of uranium atoms in a reactor core.
In the reactor, water is heated by the energy released through nuclear fission. The heat is then transferred to a separate system where water turns into steam. The steam drives a turbine, which in turn drives the generators that produce electricity.
Most nuclear power plants, including those currently operating in Sweden, use so-called light water reactor technology, primarily in the form of boiling water reactors (BWRs) or pressurised water reactors (PWRs).
Videberg Kraft has selected the reactor type and number of reactors: three modularly built pressurised water reactors with a combined thermal output of up to about 4,200 MW, expected to produce about 12 TWh of electricity per year.
Compared to traditional reactors, modular reactors have a larger share of prefabricated components that are assembled on site. This enables considerably shorter construction times and makes the technology scalable, while requiring less on-site labour than traditional reactors – which in turn drives cost savings.